Testing the Installation
Power-up and Initial Test Procedure
When the Accord control panel has been installed in accordance with the preceding
safety and wiring instructions the system should be tested. The test procedure is
outlined below.
Note: Before the test commences all auxiliary devices such as powered sensors
(PIRs), remote keypads, alarm sounders, etc, must be connected. The stand-by
battery should not be connected at this point.
Apply input power to the mains transformer. Check that the Auxiliary Voltage at
terminals AUX + and AUX – on the main terminal strip measures between 13.5 V and
14 V d.c. If the auxiliary voltage is under 13.5 V, too much current is being drawn.
For the current consumption of the control panel and keypads see Appendix A.
Note: If the auxiliary voltage is between 13.5 V and 14 V d.c., connect the battery to
the Battery Terminals, observing the correct polarity.
Further Test Procedure
Once the control panel has been installed, and the power up and initial test procedure
have been performed, it is advisable to check that the keypad(s) and ancillary devices
are operating correctly.
To test the keypad:
1. Press 1234 1 – Set.
2. Press Ö (Exit) – Panel Exits setting routine.
This ensures the keypad and control panel communicate correctly. Test each keypad in
this manner. See Section 4 for test information.
Walk Test Zones:
It is advisable to Walk Test all programmed zones, including RF zones and any zone
added after initial Power-Up.
Engineer Digicom Test:
This test allows the engineer to send a test report through the digicom. Two beeps
confirm entry of key sequence whilst a further two beeps confirm kiss off.
To send Test Report:
1. Press Engineer Code, # then 5.